Oracle Corp. has reportedly issued a force majeure notice to the developer of its Project Jupiter data center campus in New Mexico. The notice cites delays in securing adequate energy supply as the reason for the action.

VERA Brief

AI-generated. Grounded in the article and its cited sources.

Oracle Corp. has issued a force majeure notice to the developer of its Project Jupiter data center campus in New Mexico. The notice cites delays in securing adequate energy supply as the reason for the action, highlighting potential challenges in scaling data center infrastructure.

Key facts

  • Oracle Corp. has issued a force majeure notice to the developer of Project Jupiter.
  • The force majeure notice cites delays in securing adequate energy supply.
  • A force majeure clause typically excuses parties from contractual obligations due to unforeseen circumstances.
  • This development highlights potential challenges in scaling data center infrastructure concerning energy availability.